CSI Construction Update for week of 8.29.2011

 Permanent link
Excavation continues this week which involves off haul of up to 70 loads per day.  Additionally we will continue the work of underpinning at existing Harney, which involves drilling for soldier beams.  Later in the week we will being pouring concrete for footings in the southwest corner of the site.

CSI Construction Update 8.23.2011

 Permanent link
Tower crane delivery and installation was a success and is now in service within the site.  Excavation and off haul is continuing, which includes as many as 70 truck loads per day.  Please be careful when walking along Golden Gate Ave, near the entrance and exit of the job site parking lot.  In addition please be cautious while crossing the street and only cross the street using the crosswalks.  Mass excavation will continue for the next 7-10 business days with limited structural footings excavation continuing through September. 

Blogs Recent Posts

Blogs Archive