The Project BOB Website
Project BOB has been established in order to replace the University's current
ERP (Enterprise Resource Planning) system, SCT Plus, which is coming to the
end of its life.
The University's ERP system consists of Student and Financial Aid Information,
Human Resources, Finance and Advancement, along with a variety of self-service
tools. It is estimated that the migration of our existing ERP system to a new
one will take approximately 3 years.
UPDATE: June 17, 2008
Mostly Live: Most of our project modules are live now, with the teams working on post go-live issues. In progress are E-Timesheets, with a progressive summer roll-out schedule. The project officially closes in November of 2008.
|
Project BOB Mission Statement:
In support of the USF mission, the Enterprise Resource Planning Project, Project
BOB, will implement an integrated, web-based, management information system
that improves service through more efficient processes and provides the USF
community and affiliates with accurate, secure, timely and readily accessible
data.
Please check this site for new information as this project progresses.
Restricted resources for the
USF Community: log in with your USFconnect username and password
Intranet Resources for Project
BOB team members
Project BOB Information
ERP Planning and Implementation Groups
Communications to the USF Community
- March 26, 2008: HR Banner Updates
- March 25, 2008: Financial Aid Self-Service Link Going Live
- February 29, 2008: SIS Plus to be Query Only
- February 26, 2008: A Message from the Registrar
- February 5, 2008: Electronic Timesheet Training Resources
- January 25, 2008: A Message from the Graduation Center
- January 18, 2008: A Message from the President
- November 8, 2007: A Message from the Director of Financial Applications
- November 6, 2007: A Message to the University Community
- November 5, 2007: A Message from the Registrar
- November 2, 2007: A Message to the University
- October 23, 2007: A Message from the Registrar
- October 11, 2007: A Message from the Registrar
- October 10, 2007: A Message to University Students
- October 8, 2007: A Message from the Registrar
- October 5 , 2007: A Message From the President
- September 29, 2007:Training Schedule for Department Chairs and Directors
- September 25, 2007:A Message From the Registrar
- June 28, 2007: A Messasge From the Provost
- March 29, 2007: A Messasge From the President
- Fall 2006: What's Up With BOB
Newsletter
- Summer 2006: What's Up With
BOB Newsletter
- December 1, 2005: USF Signs Contract
for New Core Admin System
- September 2, 2005: Administrative
Information System Update
- July 28, 2005: Core Administrative
System (ERP) Project Update
- July 21, 2005: Core Administrative
System (ERP) Project Update
- July 15, 2005: Core Admin System
(ERP) Project Update
- July 8, 2005: USF Plans to Replace
Core Admin System
- Main Project BOB Updates
Archive: history of the updates posted to the main Project BOB website
as presented in the update box.
Project Contact Information
If you have any questions regarding the ERP Project, please feel free to
contact Beth Forest, Project Manager, ESA or Steve Gallagher, Director, ESA.
General ERP Information
ERP Steering Committee
The ERP Steering Committee reviews and approves scope, objectives, principles,
vendor(s); reviews and recommends modifications; and receives budget status
reports. This committee reports to the Board of Trustees and the President.
- Salvador Aceves, Associate Provost, Academic Affairs
- Charlie Cross, VP, Business & Finance
- John Fitzgibbons, Executive Intern, President's Office
- Margaret Higgins, VP, University Life
- BJ Johnson, Dean, Academic Services
- David MacMillan, VP, University Advancement
- Tracy Schroeder, VP, Information Technology Services
ERP Procurement Team
The ERP Procurement Team is responsible for reviewing and scoring RFP responses,
attending appropriate portions of each vendor demonstration, analyzing functional
requirements and vendor demonstration feedback and scores, participating in
vendor reference checks, and evaluating potential risks associated with each
vendor. Based on information gathered the team will evaluate the overall efficacy
of each vendor and submit to the ERP Steering Committee a vendor recommendation.
- Kim Kvaal, Finance
- Martha Peugh-Wade, Human Resources
- Archie Porter, Student System
- Kristopher Young, Advancement
- Beth Forest, ITS
- Steve Gallagher, ITS
Enterprise Systems & Applications UITC Subcommittee
Receives updates from the ERP Implementation Teams and provides input.
- Steve Gallagher, ITS
Subcommittee Chair
- Richard Beer, CPS
- Brandon Brown, A&S
- Ivy Efendioglu, B&F
- Connie Feltner, CPS
- Beth Forest, ITS
- Mary Gale, B&F
- Alan Guerrero, Law
- Michael Harrington, Planning & Budget
- Peter Helldoerfer, B&F
- Mike Hughes, Acad Services
- Karen Johnson, Gleeson Library
- Arceil Juranty, Advancement
- Jack Lendvay, A&S
|
- Larry Louie, SOBAM
- Ted Lydon, Acad Services
- Pat Lynch, Nursing
- Dan McPherson, SOE
- Dennis Miller, Univ. Life
- Susan Murphy, Acad Services
- Michael Ong, ITS
- Jim Ostrowski, Law
- Archie Porter, Acad Services
- Sue Stavn, SOBAM
- Ron Toledo, Web Services
- Kristy Vivas, Res Life
- Carole Vineyard, SOE
- Kristopher Young, Advancement
|
ERP Core Project Team
The ERP Core Project Team is made up of the leads for each of the Implementation
Teams, as well as the USF and SCT Project Managers. This team will represent the
various business units in articulating the existing business processes and specific
needs and will team with SunGard SCT's consultants to model best practices and
optimize workflows.
- Advancement
Kristopher Young, Director of Migration, University Advancement
- Finance
Ivy Efendioglu, Controller, Business & Finance
- Financial Aid
Susan Murphy, Sr. Associate Dean and Director, Financial Aid, Academic Services
- Human Resources
Martha Peugh, Associate Director, Human Resources, Business & Finance
- Student
Archie Porter, Sr. Associate Dean and University Registrar, Academic Services
- Technical
Michael Fraley, Manager, Programming & Applications, ESA, ITS
- Project Managers
SunGard SCT: Linda Wooden
USF / ITS: Beth Forest
- ITS ESA Director
Steve Gallagher
ERP Implementation Teams
The ERP Implementation Teams are responsible for the actual implementation of
the new ERP solution. There will be several teams; Banner General, Advancement,
Finance, Human Resources, Student, Financial Aid, Technical and Reporting. Each
team will consist of the appropriate department representatives and ITS personnel.