John Lo Schiavo S.J. Center for Science and Innovation - Construction News

Construction Update March 31, 2011

 Permanent link   All Posts
Underground utility locating will occur Friday April 1st in the UC lot and surrounding areas. This will allow the digging to begin to fix a broken water pipe at the northeast corner of the UC lot.   The construction fence is scheduled to be completed by April 5th.  This will allow for the demo and excavation for the installation of a cistern to begin April 11th. The existing guard shack to the east of the UC lot will be removed once a new temporary guard shack is installed in the Memorial Gym parking lot.  In preparation for the new temporary guard shack the Memorial Gym parking lot is being restriped on Friday, April 1st.  The new temporary guard shack is scheduled to be in place by mid April.  Additional updates on the removal of the existing guard shack will be coming.