Construction Update June 9, 2011

 Permanent link   All Posts

Cistern work is being completed this week with the asphalting of the UC lot on Friday.  Starting Friday, June 10th the Contractor will be drilling soldier beams, which will increase the noise levels in the plaza.  Demolition of the plaza concrete including the stairs between UC and Harney will begin Tuesday, June 14th.  Mass excavation of the plaza will follow the concrete demolition which will begin the increase numbers of dump trucks in and out of the UC lot.  Relocation of a fire hydrant next week will necessitate draining the fire sprinkler systems in Fromm and Gleeson, it will take one day and the buildings will remain occupied but will have Public Safety on fire watch.  This work will most likely be scheduled for Tuesday or Wednesday of next week, this is dependent on the schedule for the city personnel who has to come on site for this work.

 