John Lo Schiavo S.J. Center for Science and Innovation - Construction News

Construction Update June 22, 2011

 Permanent link   All Posts
The first phase of the cistern work in the UC lot is complete and the mobilization for the mass excavation has begun.  Demo of existing Harney Plaza began last week which included the demo of the stairs between Harney and UC on the 16th and 17th.  The demo of the concrete and landscaping is continuing through this week.  Mass excavation will begin in the southwest corner of the Harney Plaza Thursday, June 23rd.  With this will begin the multiple truck loads of off haul each day.  The relocation of the fire hydrant was completed last week and resulted in a wood ramp over the hose on the paver pathway between Gleeson and Harney Plaza to allow the contractor to still use the hydrant to keep the site wet during excavation.  The installation of fence lighting and speakers is occurring this week and will continue through out the week of June 27th.  The delivery and installation of the tower crane will be over a weekend in the month of July and is tentatively set for July 30th and 31st. 

Blogs Recent Posts

Blogs Archive