Underpinning at Harney is continuing this week and will continue through the next one to two weeks.  This will include very loud chipping noise due to the need to chip away at a portion of the concrete footing for Harney.  The first large concrete pour is set to occur on Thursday, September 22 in the southwest corner of the site.  The concrete pumps will be installed soon as they will be pouring the base for the concrete pump this week.  Limited excavation activities will continue and should be completed by the end of the month, though minor excavation for footings shall continue into mid October. 