Permanent link All PostsConcrete pours continue at the site. Concrete pours will generally be every 6 days. Waterproofing at existing Harney will be completed this week. Workers are continuing to remove existing waterproofing at UC to prep for new waterproofing to be installed. Major earthwork shall be completed before Christmas as the contractor digs down in between Harney and UC for the basement level of the new building.